The Gleddings School
The Gleddings School: 2016 revitalisation of a sand filled MUGA.
The infill was contaminated and SMS removed 2 tons. The surface was chemically treated for moss and algae. The surface was scarified, then decompacted and infill aerated to a minimum depth of 5mm. Power vacuum and infill cleaning of carpet pile was carried and a final scarification to ensure correct pile height clearance. The work was then completed with BSEN 15330 independent UKAS testing.